Construction work on Herat section of TAPI project nears completion

Published

on

Construction work on the Herat section of the Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipeline project has made significant progress, with approximately 92 percent of the work completed so far.

According to available information, 142.9 kilometers of the total 150-kilometer pipeline planned across Afghan territory have been laid and welded, leaving only eight kilometers of pipeline to be completed.

Meanwhile, the installation of essential pipeline equipment and the construction of related facilities have also made considerable progress. Construction of the gas offtake station and metering station in Guzara District of Herat Province is approximately 55 percent complete.

In addition, hydrotesting has been completed along approximately 70 kilometers of the laid pipeline, while testing of the remaining sections is underway in different stages. The installation of valves along the pipeline route and the construction of crossings have also been completed.

The Ministry of Mines and Petroleum and TAPI Pipeline Company Limited are jointly working to complete the construction of this major regional project by the end of the current calendar year, in line with the established schedule.

Meanwhile, the survey of routes for secondary pipelines and related facilities, aimed at establishing an internal gas distribution and regulation network in Herat city, has also been completed. Efforts are underway to begin the practical construction of the network soon.

The TAPI project is considered one of Afghanistan’s key initiatives for promoting economic growth, ensuring energy supplies, creating employment opportunities and strengthening regional cooperation.